Molten iron rushes and steel flowers shine brightly~Lingang Phase II project enters the stage of comprehensive hot trial production

Time:2025-08-12Browse:

On March 26th at 19:07, under the joint witness of relevant leaders from provinces, cities, counties, and Lingang District, the design unit MCC Saidi, the construction unit China First Metallurgical Group Corporation, the supervision unit Mai Century, as well as participating units and equipment manufacturers, the expert team of Baosteel Group of China Baowu Group, company leaders, unit leaders, and employees, the No. 3 blast furnace of Yongfeng Lingang Company was successfully ignited, marking the completion of the key node of Yongfeng Lingang Phase II project and entering the stage of comprehensive hot testing and production

On March 27th at 13:03, the fiery red molten iron flowed out along the iron groove of the blast furnace, and the first batch of molten iron was successfully produced by the No. 3 blast furnace.


On March 27th at 17:07, the 250 ton converter at the steel plant was successfully started. 17: 55. The first batch of molten steel was smelted in the converter, and enthusiastic applause rang out on site.
After full production, the main business of the group's steel industry will shift from high-quality long materials to high-quality sheet metal series, which will provide good support for achieving high-end products, intelligent operations, green environment, and industrial clustering, laying a more solid foundation for achieving green, low-carbon, and high-quality development.